Site datum + slab check
Establish the project datum and check the concrete base. The current instructions specify a reference deviation of no more than 5 mm under a 2 m straightedge.
Start Flooring Brief
ATHREN Timber · Installation Planning
A structured interpretation of the current single- and double-batten installation instructions, with disputed details deliberately held for project confirmation.
Installation sequence
The current documents make slab level, batten set-out, moisture control, movement and ventilation part of the complete floor system rather than installer afterthoughts.
Establish the project datum and check the concrete base. The current instructions specify a reference deviation of no more than 5 mm under a 2 m straightedge.
Remove loose mortar and debris, survey the base and identify local height differences before timber installation starts.
Set out the timber support lines to the approved project drawing. Current installation references use a 400 mm planning grid in the batten layout.
Fit the lower rubber levelling / shock-support elements. Exact spacing is held for the selected construction before installation.
Install the single batten layer or the lower + upper batten arrangement for the double system, then complete accurate levelling.
Lay the solid-pine subfloor approximately 45° to the timber battens, with documented gaps between rough-board rows.
Install the 0.5 mm EPE membrane with joints taped and arranged to avoid unsuitable overlap.
Lay the finished boards in the approved venue orientation, using the specified fixing method and movement provisions.
Provide perimeter expansion and the project-specific intermediate movement / ventilation details shown in the current installation instructions.
Important: the available installation references contain conflicting rubber-pad spacing references. The public installation guide therefore does not publish a final pad spacing until the approved project installation information is issued.
ATHREN · technical diagrams
These original diagrams translate the current installation documents into a clean ATHREN planning language. They show documented layer order and nominal build heights, while disputed spacing and model-specific performance remain deliberately unlabelled.
Birch playing surface over moisture control, solid-pine subfloor, timber battens and resilient rubber support.
Two timber batten layers separated by intermediate resilient pads, over a lower resilient levelling layer.
Current instructions document a ≤5 mm / 2 m base check, perimeter expansion, intermediate movement provisions and finished-floor ventilation.
Before release
Finished-floor level, slab moisture, underfloor services, wall interfaces, sockets and court equipment should be coordinated before the batten layout is frozen.
Direct project answers
Installation planning for sprung timber sports floors covering datum and slab checks, cleaning, batten set-out, resilient supports, timber layers, 19 mm…
Typical project pathways include residential projects, commercial projects, hospitality projects, and international projects. Final suitability depends on the exact configuration, site conditions, operating requirements and destination.
Before specification or quotation, the project review should confirm: Verified product specifications or documented product facts; Clear applications, limitations and configuration boundaries; Project inputs required for manual quotation or technical review; Apollo supply-only scope and purchaser/local-project responsibilities. Claims are kept tied to the exact proposed system rather than transferred from a related product or reference configuration.
Apollo can supply suitable projects internationally where the product and destination pathway are current. Send the project location, intended use, dimensions or quantities, timing, relevant drawings or photographs, and any known performance, compliance or environmental requirements for review.